The following is a suggested list of milestones for your projects. It is imperative to stay close to these deadlines and milestones in order to ensure proper completion of your project. The dates are approximate.

  1. February 4:


  2. The names of the group members.

  3. February 11:


  4. The name of the Manager and the QA Manager and an introductory letter on your project. Design of a web page with all the information.

  5. February 25:


  6. Description of the system and list of the use cases that your system will implement. These can be written informally, they need not to be written in UML notation.
    1. Feasibility study
    2. Requirements description

  7. March 6:


    1. Specification document

  8. March 27


    1. Design Document

  9. April 17


    1. Compilable Code
    2. Test Plan


  10. April 24-29:


    1. Presentation of Project

  11. April 29:
    1. Formal Demonstration of Project
    1. As-built version of Specification Document, Design Document, Test Plan and Source Code





Christelle Scharff
cscharff@pace.edu
New York City Campus
Computer Science and Information System Department
156 William Street
Floor 12 - 1204 B
New York, NY
212-346-1849 (Tel)
212-346-1863 (Fax)

Class time: Tuesday 6:00-8:40pm
Room: W510
Office hours: Monday 3:30-5:30 pm, Tuesday 4:45-5:45 pm, Wednesday 2:30 - 4:30 pm and by appointment